From Raw Ground to Recorded Lots: A Land Developer's Operating Checklist
From 1996 to 2009 I led Home Free, Inc., a Utah company that took raw land all the way to finished homes. We bought the ground, carried it through approvals, put in the utilities, subdivided it and built the houses. At our peak we had up to 57 jobsites running at once. I've told the story of those Utah years elsewhere. This piece is the checklist I'd hand an owner looking at a parcel today.
Land development is where a builder makes the money that later shows up as "margin" on a house, and it's where a builder can get hurt the worst. The house is the visible part. The land is where the capital and the time hide.
1. Price the clock before you price the dirt
The first question isn't "What does the land cost?" It's "How long will I own it before I sell a lot?" Every month of approvals, engineering and infrastructure is a month of interest, taxes and insurance with no revenue. I learned to write down a realistic carrying timeline first, then the purchase price that timeline can support. If an owner can't say with a straight face how long approvals will really take in that jurisdiction, the deal isn't ready.
Checklist:
- Monthly carrying cost (interest, taxes, insurance, maintenance)
- Realistic approval timeline, plus a slip case
- The price at which the deal still works if the slip case happens
2. Approvals are a project, not a waiting room
Developers often treat approvals as something that happens to them. Treat it like any other project, with a schedule, an owner and a next action every week. Know the sequence of submittals, who reviews them, what the meeting calendar looks like, and what has typically drawn comments. A missed submittal deadline can cost a month. That month has a dollar figure, and you calculated it in step 1.
3. Utilities decide the plan
Water, sewer, power and access shape what you can build and when you can build it. Before you fall in love with a lot layout, find out where service comes from, what capacity exists, who pays for extensions and how long the utility takes to design and inspect. Many "great deals" on raw land are great because the utilities are far away or expensive.
Checklist:
- Source and capacity for water, sewer, power and roads
- Who pays for extensions, and when
- Utility design and inspection lead times on the schedule
4. Subdivide for the market you'll actually sell into
Lot count isn't the goal. Sold lots and sold homes are. We sold homes every way a builder can: pre-sold, build-to-order, investor builds and specs. Each one has a different buyer and a different cash profile, and the lot plan should reflect the mix you expect. A layout that maximizes lot count but produces lots nobody in your price band wants is a carrying-cost machine.
5. Phase the infrastructure to the sales pace
Putting in every road and utility on day one looks efficient on a bid sheet. But it front-loads capital you won't recover until lots sell. Phasing lets sales fund the next phase, as long as the engineering and approvals were designed for phasing from the start. Decide that early. Retrofitting phases later is expensive.
6. Run construction as one schedule
Once lots are ready, building many homes at once is a scheduling problem, not a heroics problem. Every house follows the same sequence. The work is knowing where every job sits in that sequence each morning and protecting the handoffs between trades. With 13 full-time subcontractors and a small staff, that discipline was the only way to keep dozens of jobs moving.
7. Watch the capital every week
The developers who get in trouble usually knew the numbers once, at purchase. The ones who do well look every week: spend to date against budget, lots under contract, closings scheduled, cash needed for the next phase. It isn't glamorous. It's the difference between a project that funds itself and one that funds the bank.
The short version
Price the clock, run approvals like a project, let utilities shape the plan, subdivide for real buyers, phase infrastructure to sales, run construction as one schedule, and watch the cash weekly.
If you're evaluating a parcel or a development that's stalled, I'm glad to take a look. See how I work with developers or get in touch.
Richard T. French is an operations executive and advisor in the Richmond, Virginia area. He led Home Free, Inc. in Utah from 1996 to 2009 and owns Home Free LLC (homefree.pro).